ACTIVITIES:
All the containerized electrical substations (total surface equal to 1920 sqm) are fully
complete as described below.
– HVAC System
– Fire detection and fire-fighting system
– Lighting & Small Power Distribution (including Distribution panels)
– Packing (where necessary), suitable for Track transportation
Equipment – Hammar 1:
• N.1 Building (Electrical Room), complete with n.9 Modular Container Units;
• N.1 11kV Switchgear Metal Clad Type;
• N.5 400V Switchboards PC/MCC Type;
• 230V AC UPS – 120kVA;
• 110V DC UPS – 50A;
• N.4 2500kVA, 11/0,425kV Transformers + NERs;
• N.1 250kVA, 400/425V Lighting Transformer;
• N.1 75kVA, 400/425V Lighting Transformer.
Equipment – Hammar 2:
• N.1 Building (Electrical Room), complete with n.4 Modular Container Units;
• N.1 6,6kV Switchgear Metal Clad Type;
• N.1 400V Switchboard PC/MCC Type;
• 110V DC UPS – 50A;
• N.2 25MVA, 11/6,9kV Transformers + NERs;
• N.2 2000kVA, 11/0,425kVA Transformers;
• N.1 150kVA, 400/425V Lighting Transformer;
• N.1 75kVA, 400/425V Lighting Transformer.
Equipment – Hammar 3:
• N.1 Building (Electrical Room), complete with n.1 Modular Container Unit;
• N.1 400V Switchboard PC/MCC Type;
• N.2 3150kVA, 11/0,425kVA Transformers;
• N.1 150kVA, 400/425V Lighting Transformer;
• N.1 75kVA, 400/425V Lighting Transformer;
Equipment – Hammar 4:
• N.1 Building (Electrical Room), complete with n.1 Modular Container Unit;
• N.1 400V Switchboard PC/MCC Type;
• N.2 2000kVA, 11/0,425kVA Transformers;
• N.1 150kVA, 400/425V Lighting Transformer;
• N.1 75kVA, 400/425V Lighting Transformer.
Equipment – Hammar 5:
• N.1 Building (Electrical Room), complete with n.1 Modular Container Unit;
• N.1 400V Switchboard PC/MCC Type;
• N.2 2000kVA, 11/0,425kVA Transformers;
• N.1 150kVA, 400/425V Lighting Transformer;
• N.1 75kVA, 400/425V Lighting Transformer.
Equipment – Zubair/Rafidiya 1:
• N.1 Building (Electrical Room), complete with n.7 Modular Container Units;
• N.1 11kV Switchgear Metal Clad Type;
• N.4 400V Switchboards PC/MCC Type;
• 230V AC UPS – 58kVA;
• 110V DC UPS – 50A;
• N.2 2500kVA, 11/0,425kVA Transformers + NERs;
• N.2 2000kVA, 11/0,425kVA Transformers;
• N.1 250kVA, 400/425V Lighting Transformer;
• N.1 75kVA, 400/425V Lighting Transformer.
Equipment – Zubair/Rafidiya 2:
• N.1 Building (Electrical Room), complete with n.2 Modular Container Unit;
• N.1 6,6kV Switchgear Metal Clad Type;
• N.1 400V Switchboard PC/MCC Type;
• N.4 MV Variable Frequency Driver;
• 110V DC UPS – 50A;
• N.2 7,5MVA, 11/6,9kVA Transformers + NERs;
• N.2 1000kVA, 11/0,425kVA Transformers;
• N.1 160kVA, 400/425V Lighting Transformer;
• N.1 75kVA, 400/425V Lighting Transformer.
Equipment – Zubair/Rafidiya 3:
• N.1 Building (Electrical Room), complete with n.1 Modular Container Unit;
• N.1 400V Switchboard PC/MCC Type;
• N.2 1600kVA, 11/0,425kVA Transformers;
• N.1 160kVA, 400/425V Lighting Transformer;
• N.1 75kVA, 400/425V Lighting Transformer.
Engineering:
• CT & VT study;
• Engineering and drawings;
• Protection coordination & setting study for digital relays in scope of supply;
• Furnishing protection relay coordination & calculation;
• Factory Acceptance Tests;
• Training.